top of page

Medical Device Sales Center Application Period: Examination, On-Site Inspection, Remedying Deficiencies, Personnel Changes and Closure Periods

12 hours ago
8 min read
tıbbi cihaz satış merkezi başvuru süresi ve iş günü takvimi

SUMMARY

The sales center application period is regulated in Article 6 of the Tıbbi Cihaz Satış, Reklam ve Tanıtım Yönetmeliği (Medical Device Sales, Advertising and Promotion Regulation). The documents are examined within fifteen working days from the application date; if there is no deficiency, an on-site inspection is carried out within forty-five working days from the application date.

This article deals only with the periods: document examination, on-site inspection, remedying deficiencies and rejection, issuing the authorization certificate, relocation and assignment, personnel change notifications and closure. All periods are given as direct quotations from the Regulation and the TİTCK Guideline TCS-KLVZ-08.

For your ÜTS company, document and product registrations after the authorization certificate: Medical Device ÜTS Registration Consultancy

Contents

1. Start of the Periods: Application Date

The application is made to the provincial health directorate by petition. Article 5, paragraph 1 of the Regulation:

“(1) A natural or legal person wishing to be authorized as a sales center applies to the Directorate with a petition containing the address, title and ownership information of the sales center.”

Under Article 4, the Directorate is the provincial health directorate:

“h) Directorate: The provincial health directorate,”

The document examination and on-site inspection periods in Article 6 start from the application date. How the application date is to be documented is not separately regulated in the Regulation or in the TCS-KLVZ-08 guideline. For the documents in the application file, see our article on the sales center authorization certificate application file.

2. Document Examination: Fifteen Working Days

“(1) The documents prepared in accordance with Article 5 are examined by the Directorate within fifteen working days from the application date. If there is a deficiency in the application, it is notified to the sales center in writing. If there is no deficiency in the application, an on-site inspection is carried out by the Directorate within forty-five working days from the application date.”

  • Document examination: fifteen working days from the application date.

  • If there is a deficiency in the application, it is notified to the sales center in writing.

  • The periods are written in working days.

3. On-Site Inspection: Forty-Five Working Days

If there is no deficiency, the on-site inspection is also counted from the application date; the period is forty-five working days. If the conditions are met, the authorization certificate is issued:

“(2) If, in the on-site inspection carried out, the sales center meets the conditions defined in this Regulation, an authorization certificate is issued by the Directorate.”

For the physical requirements checked in the on-site inspection, see our article on sales center physical requirements.

4. Remedying Deficiencies and Rejection: Forty-Five Working Days

  • “(3) If, in the on-site inspection, the sales center does not meet the conditions defined in this Regulation, the deficiencies are notified to the applicant by means of an inspection report. The sales center may remedy these deficiencies within forty-five working days following the date of notification of the inspection report containing the deficiencies and apply again to the Directorate by petition to obtain authorization. Following the application, the provision of the second paragraph applies.”

  • “(4) The applications of those who do not reapply for authorization within forty-five working days following the date of notification of the first inspection report to the applicant, and of those whose commencement of activity is not found appropriate as a result of the second evaluation made by the Directorate, are rejected.”

  • The period for remedying deficiencies starts from the date of notification of the inspection report and is forty-five working days.

  • The reapplication is made by petition.

  • The application of those who do not reapply within the period is rejected.

  • The application of those not found appropriate in the second evaluation is rejected.

5. Issuing the Authorization Certificate

Article 7 of the Regulation ties the issuing of the certificate to the submission of the original payment receipts. The Regulation does not state a separate number of days for this step:

“(1) After the sales centers found to comply with the provisions of this Regulation as a result of the inspection submit to the Directorate the work certificates of the responsible manager, the sales and promotion staff member and, if any, the clinical support staff member, and the original receipts showing that the fees for the sales center authorization certificate have been paid, the Directorate issues the authorization certificate together with the work certificates of the responsible manager, the clinical support staff member and the sales and promotion staff member, and their identity cards, and delivers them to the responsible manager.”

Under Article 5 of the TCS-KLVZ-08 guideline, the authorization certificate is issued according to the Annex-2 model:

“(1) For natural or legal persons whose application is found appropriate as a result of the evaluation of applications made to be authorized as a medical device sales center, the Directorate issues the Medical Device Sales Center Authorization Certificate (“Tıbbi Cihaz Satış Merkezi Yetki Belgesi”) in Annex-2.”

6. Periods Restart on Relocation and Assignment

Under Article 32 of the Regulation, Articles 6 and 7 apply again to relocation and assignment applications within the same province:

  • “(1) If sales centers are relocated to another address within the same province, the operator or the responsible manager applies to the Directorate with the business opening and operating license to be obtained from the relevant authority for the address to which it will be relocated and a relocation request petition. Following the application, the necessary procedures are carried out in accordance with Articles 6 and 7.”

  • “(2) In case of assignment of the sales center, the assuming sales center applies to the Directorate with a copy of the assignment contract and the documents stated in the application for the authorization certificate. Following the application, the necessary procedures are carried out in accordance with Articles 6 and 7.”

For the other conditions of relocation and assignment, see our article on sales center relocation, assignment and closure.

7. Personnel Change Notification Periods

The general period for changes in personnel for whom a work certificate has been issued is in Article 8, paragraph 7:

“(7) The sales center notifies the Directorate of changes in personnel for whom a work certificate has been issued within five working days.”

For the responsible manager, Article 10, paragraph 8:

“(8) (Amended: Official Gazette 2 September 2020-31232) If the responsible manager’s duty is terminated, the responsible manager resigns, or loses in any way the conditions required to serve as responsible manager, the sales center must notify the Directorate within ten working days from the occurrence of such a situation, or within twenty working days in case of the person’s death. A new responsible manager must also be appointed within thirty working days at the latest from the determination of the situation. If the sales center does not appoint a new responsible manager within this period, the medical device sales activity of the center concerned is temporarily suspended until a new responsible manager is appointed.”

For the sales and promotion staff member, Article 11, paragraph 6:

“A new sales and promotion staff member must also be appointed within sixty working days at the latest from the determination of the situation.”

  • Change in personnel with a work certificate: notification within five working days.

  • Responsible manager: notification within ten working days (twenty working days in case of death), new appointment within thirty working days.

  • Sales and promotion staff member: notification within ten working days (twenty working days in case of death), new appointment within sixty working days.

  • If no appointment is made within the period, sales activity is temporarily suspended.

For personnel requirements, see our articles on sales center responsible manager and sales and promotion staff member.

8. Closure Periods

For an operator who wishes to close the sales center, Article 32, paragraph 5:

  • “a) The request to close the sales center is notified to the Directorate in writing at least one month in advance.”

  • “b) Activity continues for at least fifteen working days from the closure application to the Directorate, and during this period a notice informing about the closure process is posted at the entrance and in various places of the sales center.”

  • “c) The operator of the sales center delivers the authorization certificate and the work certificates and identity cards issued under this Regulation to the Directorate within three working days from the actual closure date.”

9. Relationship of the Periods with ÜTS

Under Article 5 of the ÜTS registration guideline TCKKD-KLVZ-03, a company registration of the type “Üretici/İthalatçı/Bayi/İhracatçı” (Manufacturer/Importer/Dealer/Exporter) depends on the sales center license and the ÇKYS number:

“In other words, companies that will make a company registration of the type “Üretici/İthalatçı/Bayi/İhracatçı” in ÜTS must hold a medical device sales center license, and the ÇKYS number must be entered during company registration.”

When the responsible manager, title and address are updated in ÇKYS, they are reflected automatically in ÜTS:

“(7) Where the responsible manager, title and address of the company change, if the relevant information is updated in ÇKYS, these changes are updated automatically in ÜTS.”

Under Article 11 of the TCS-KLVZ-08 guideline, ÜTS procedures are also tied to a period for sales centers whose activity is suspended or closed:

“(5) The ÜTS registration and notification procedures of sales centers whose activity is temporarily suspended in line with the provisions of the Regulation are blocked for the duration of the sanction. The ÜTS registration procedures of sales centers closed indefinitely in line with the provisions of the Regulation are stopped, thirty days are given for the notification procedures of their existing devices, and the notification procedures are also blocked at the end of this period.”

For suspension periods imposed as a result of an inspection, see our article on sales center inspection, for company registration, ÜTS company registration, and for the application, our page on sales center authorization certificate application support.

10. Frequently Asked Questions

How long does the provincial health directorate take to examine the application?

Under Article 6/1 of the Regulation, the documents are examined within fifteen working days from the application date. If there is a deficiency, it is notified in writing.

When is the on-site inspection carried out?

If there is no deficiency in the application, it is carried out within forty-five working days from the application date.

How long is there if a deficiency is found in the on-site inspection?

Within forty-five working days from the date of notification of the inspection report, the deficiencies may be remedied and a new application made by petition. The application of those who do not apply within the period is rejected.

Within how many days must it be notified if the responsible manager leaves?

Under Article 10/8, it is notified within ten working days, or twenty working days in case of death; a new responsible manager is appointed within thirty working days at the latest.

Do the periods restart in a relocation application?

Yes. Under Article 32/1, following the relocation application, procedures are carried out in accordance with Articles 6 and 7.

For your ÜTS company, document and product registrations after the authorization certificate: Medical Device ÜTS Registration Consultancy

Sources

 
 

Medical Device ÜTS Registration Consultancy

Request an ÜTS registration consultancy quote

Ehlibeyt Mahallesi, Tekstilciler Caddesi No: 35/7 06520 Çankaya / Ankara - TÜRKİYE

Cevizli Mahallesi, Zuhal Caddesi Ritim İstanbul B Blok, No:44 Maltepe / İstanbul - TÜRKİYE

info@medexmedikal.com
+90 505 580 4622
+90 312 389 1354

ÜTS Guides · Legislation Calendar · Glossary · ÜTS Guide Index · Frequently Asked Questions

Services: ÜTS Consultancy · Who Carries Out the ÜTS Registration? · ÜTS Document Registration Consultancy · ÜTS Product Registration Consultancy · Importer ÜTS Registration Consultancy · Sales Centre Authorisation Certificate · EUDAMED Registration Consultancy · MDR/IVDR Declaration of Conformity · Technical File Preliminary Review · Label and Instructions for Use Check · PRRC Service · PMS and PSUR · Clinical Evaluation · EMDN and GMDN Code Determination · Certificate of Free Sale · EUDAMED XML Generator · ÜTS Registration Training · Correction of a Rejected ÜTS Application

KVKK and Privacy Policy | Cookie Policy | Accessibility Statement

© 2026 Medex Kurumsal Danışmanlık Ltd. Şti.

bottom of page
WhatsApp Hemen Ara