Getting ÜTS Registration Done
Your devices are waiting at customs or in the warehouse, ÜTS registration is needed to place them on the market, and nobody in the company knows how to do this work. Will you do it with your own team
Getting Your ÜTS Registration Done: Authorised Persons, the Consultant's Role and the Process
Your devices are waiting at customs or in the warehouse, ÜTS registration is needed to place them on the market, and nobody in the company knows how to do this work. Will you do it with your own team or have an outside consultant do it? This page explains both options in concrete terms.
The answer is not as simple as "hire a consultant" or "do it yourself". Some steps of ÜTS registration can be delegated, while others remain with the company itself by law. Below you will find which step sits on which side, together with its legal basis.
ÜTS Registration Is Actually Three Separate Jobs
"ÜTS registration" is spoken of as a single transaction, but there are three separate jobs in the system, and all three are regulated in separate articles, on separate screens and with separate limits.
Company registration: Regulated in Article 5 of the Guide on the Registration Processes of Medical Devices to the Product Tracking System. Company registrations are carried out on the basis of MERSİS or VEDOP; if a company has both a MERSİS and a VEDOP number, the transaction is carried out under the MERSİS number.
Document registration and document application: Regulated in Article 39 of the Guide. The document application is made from the "Create Document Application" field on the "Document Application Transactions" screen under the "Document" tab, and one document application contains at most 5 document notifications.
Device registration and device application: Regulated in Article 40 of the Guide. The device application is made from the "Medical Device Application Transactions" screen under the "Medical Device" tab; optical, active implantable, Class 3 and other product applications contain at most 500 device notifications, while custom-made device and system procedure pack applications contain at most 5 notifications.
The order is mandatory. Paragraph 5(a) of Article 25 of the Guide states that in device registration only documents registered in ÜTS as a result of an application made under Article 39 can be selected in the "Documents" field. Paragraph 11 of the same article and paragraph 1 of Article 40 require a device application under Article 40 for the device to reach "Registered" status. In other words, a device registration is not possible before the document registration is completed, and "Registered" status is not possible without a device application.
Doing It with Your Own Team: Required Competence and Legal Conditions
Doing the registration with your own team is possible, and many companies run it this way. But you need to see the real weight of the work.
The registration screens are not free-text screens. Paragraphs 2 to 10 of Article 25 of the Guide, for devices under the former regulations, and paragraphs 2 to 11 of Article 27, for devices under MDR, list the fields on the ÜTS registration screen heading by heading and add a note for each field, such as "mandatory field to be entered in ÜTS" or "mandatory selection field". Most fields, such as product name, GTİP number, country of origin, GMDN, EMDN, branch type, sterilisation method, measurement type, storage condition and product images, are mandatory, and how each is to be filled in is described in separate sub-items.
The second burden is the document business rules. Articles 63 to 67 of the Guide determine which documents are linked to a device according to the device's regulation and risk class, and refer to a separate Annex for each class: Annex 81, Annex 82 and Annex 83 under MDD; Annex 84 under AIMDD; Annex 85, Annex 86 and Annex 87 under IVDD; Annex 88 to Annex 93 under MDR; and Annex 94 to Annex 100 under IVDR. If a document combination that does not suit the device's class is selected, the system does not move the application forward.
Mandatory Training for Staff Who Carry Out Registration in ÜTS
This is a condition most companies planning to proceed with their own team do not know about. Paragraph 10 of Article 26 of the Medical Device Sales, Advertising and Promotion Regulation states that persons who carry out medical device registration transactions in the Agency's registration and information management system on behalf of a sales centre must successfully complete the training determined by the Agency.
Paragraph 2 of Article 28/A of the same Regulation defines the sanction: if it is determined that transactions have been carried out repeatedly in the Agency's registration and information management systems contrary to the procedures and principles determined by the Agency, the training received by the persons carrying out these transactions under paragraph 10 of Article 26 is cancelled.
In other words, the person who registers in ÜTS is not merely a staff member who knows how to use the system; they have completed training and carry the risk of losing it. When proceeding with an in-house team, you need to make sure this condition is met.
The Career Value of Two Years of Registration Experience in ÜTS
The same Regulation also contains a benefit for staff who do this work. Paragraph 5 of Article 33 states that, for persons who have successfully completed the training under paragraph 10 of Article 26, have carried out medical device registration transactions in the Agency's registration and information management system on behalf of a sales centre for at least two years, and wish to serve as a sales and promotion staff member, the provision in paragraph 2 of Article 11 will not be required, provided that they are at least secondary school graduates.
Paragraph 2 of Article 11 requires the sales and promotion staff member to be a graduate of a college providing vocational education and training at least at associate degree level. Therefore, a secondary school graduate who has carried out registration transactions in ÜTS for two years does not have to meet this associate degree requirement to become a sales and promotion staff member. For companies building an in-house team, this is a provision that also affects staff's long-term career planning.
Having a Consultant Do It: The Authorisation Model in ÜTS
The second route is to have the work done by a consultant who knows ÜTS. The set-up here is not files going back and forth by email: the consultant works as an ÜTS user of your company.
The model works as follows. The company's users and signatory authorities defined in ÜTS are managed on the company's own side; paragraph 6 of Article 5 of the Guide, by stating that the signatory authorities and users defined in ÜTS must be updated so that ÜTS activities can continue in company transfers and mergers, shows that this list is the company's responsibility. The company defines the consultant as a user of the "Medical Device Registration Officer" type from its own company page. With this authorisation, the consultant creates the company, document and product records and performs the "Approve" action on the application summary screens.
The limit of the model is drawn at the same place: the e-signature step remains with the company's signatory authority. This is not a preference but a structure set up by the Guide.
Work That Can Be Delegated: the "Medical Device Registration Officer" Authorisation
Paragraph 11 of Article 39 of the Guide states, for the document application: the "Approve" action is carried out on the "Document Application Summary" screen, and only users of the relevant company of the "Medical Device Registration Officer" type can carry out this action.
The same sentence is repeated for device applications in paragraph 5(f) of Article 40, and for custom-made medical device and system procedure pack applications in paragraph 6(c). In all three places the authority is tied to a single user type.
The practical meaning of this is that the party that creates and approves the application is this user type. The authorisation opened for the consultant is exactly this. Filling in the registration screens, uploading documents, setting up the document combination that suits the business rules, preparing bulk upload files, and creating and approving the application are the jobs carried out under this authorisation.
Work That Cannot Be Delegated: the Signatory's E-Signature
Paragraph 13 of Article 39 of the Guide is clear: an application in "Awaiting Signature" status is signed electronically by the company's applicant signatory authority. For device applications as well, paragraph 5(g) of Article 40 requires that, for the application to go to the Agency in "Under Review" status, it must first be signed electronically by the company's signatory authority.
For domestic manufacturer documents this condition is even stricter. Paragraph 2(a) of Article 9 of the Guide requires the undertaking in Annex 21 to be e-signed on behalf of the company by the person registered in ÜTS as "Responsible Manager" or "Signatory Authority". The first sub-item of paragraph 1(ç) of Article 13 adds: ÜTS allows a document application only if the document concerned is electronically signed by the "Responsible Manager" or "Signatory Authority".
In short, the e-signature step is tied to the company at system level. No consultancy set-up can change this, and you should not enter into any arrangement that proposes to change it.
Who Remains Responsible for the Accuracy of the Data?
The answer to this question is written in paragraph 4 of Article 31 of the Medical Device Sales, Advertising and Promotion Regulation. The Agency issues guides on the registration of devices in the registration and information management system; sales centres set up the infrastructure in accordance with these guides within the specified periods and register the devices in the system. The last sentence of the paragraph is this: the accuracy of the information on the devices registered in the system is the responsibility of the sales centre that made the product registration.
This responsibility does not disappear with consultancy. The consultant creates the record, but the data in the system stands as the company's declaration. A healthy consultancy relationship is therefore built on transparency: what was entered in which field, which document was linked to which device and which application went under which number are reported in a way the company can see. The company's ability to see all records from its own ÜTS account is the natural control mechanism of this relationship.
The Real Scope of the Work: What Is Done on Which Screen?
Seeing the process by screen names makes it easier to estimate the size of the work.
Document Application Transactions: According to paragraph 2 of Article 39 of the Guide, it is under the "Document" tab; the document application is created here.
Medical Device Application Transactions: According to paragraph 2 of Article 40, it is under the "Medical Device" tab; the device application type is selected here.
List My Medical Devices: According to paragraph 2 of Article 34, it is the screen where bulk transactions are started; devices in "Ready for Application" status are also listed here.
Bulk Transactions: The area under the same screen; bulk addition, update and deletion of devices are carried out here.
Free Sale Certificate Application Transactions: According to paragraph 2(a) of Article 42, it is under the "Medical Device" tab; the application for the certificate required for export is made here.
Submit Request: The screen defined in paragraph 16 of Article 39; requests to add codes and values, and objections to rejection, revision and update decisions, are submitted here.
Process Visibility, Not a Promise of Time
No source says ÜTS registration "finishes in so many days", because the Guide defines no such period. The periods that appear in the Guide are periods given to the parties:
3 days: The update period tied to the "Request Update" decision in paragraph 17 of Article 39.
45 days: The revision period applied to certificates found not to be up to date, in paragraph 18(a) of Article 39.
120 days: In the same subparagraph, the extension applied only to EU certificates under MDR and IVDR and only to certificates revised because of an extension of product scope.
5 days: In paragraph 3 of Article 43, the period within which other companies holding records with the same barcode state their opinion on an imported product data change request.
10 days: In paragraph 2(ö) of Article 42, the period within which payment for the free sale certificate must be made.
None of these periods is a completion time for the work. In consultancy, the right promise is not time but visibility: the number, status and next step of each application are known; periods based on a source are entered in the calendar; and no date that is not in the source is given.
Cost Items: Which Applications Are Chargeable?
Paragraph 13(a) of Article 39 of the Guide determines which applications are subject to a fee by document type: applications containing any of the document types mentioned in Articles 6, 7, 10, 11 and 14 of the Guide move to "Awaiting Payment" status and do not move to "Under Review" until the fee is paid and approved. These are documents of the certificate and declaration type. For device applications as well, paragraph 5(g) of Article 40 makes the payment step mandatory.
For the free sale certificate, charging is per copy. Paragraph 2(c) of Article 42 of the Guide states that a separate application fee is charged for each copy entered in the "Number of English Copies" field, and subparagraph (e) states that a fee is also charged for the Turkish free sale certificate if a Turkish copy is also requested. Determining in advance how many copies are needed for how many countries in your export plan directly affects this item.
Documents to Collect Before Starting
The only thing that speeds up the process is having the file complete before you start.
For imported devices, to be collected: the approved EC or EU certificate in line with paragraphs 1 and 2 of Article 8 of the Guide (apostilled, consulate-approved, e-apostilled or the e-signed original) and its Turkish translation by a sworn translator; the declaration of conformity or EU declaration of conformity in line with paragraph 1 of Article 12 and its translation; where the manufacturer is established outside the EU and Türkiye, the EU authorised representative's mandate under paragraph 7 of Article 12; and instructions for use in line with paragraph 1 of Article 18.
2026/KKB-2 update: With TİTCK's Announcement No. 2026/KKB-2 dated 02.11.2026, a new route was introduced in place of the option of uploading the manufacturer's e-signed original for the declaration of conformity and the SİP declaration of a foreign manufacturer:
"it has been decided to apply the option of uploading the document concerned to the relevant field in ÜTS together with an undertaking electronically signed, by an authorised person of the importer company authorised by the foreign manufacturer, with an e-signature (secure e-signature) created on the basis of a qualified electronic certificate obtained from an electronic certificate service provider recognised by Türkiye." (unofficial translation)
Source: TİTCK Announcement No. 2026/KKB-2. Required documents and steps: ÜTS document registration guide.
On the company side, to be collected: under paragraph 5 of Article 5 of the Guide, companies registering as "Manufacturer/Importer/Dealer/Exporter" must hold a medical device sales centre licence and must enter the ÇKYS number during company registration. Signatory authority details and the availability of the e-signature must also be ready at this stage. If the company type is "Ordinary partnership", paragraph 3 of Article 5 introduces an additional step: for the company registration to be completed, a company registration application must also be made via EBS, and the original or notarised copy of the ordinary partnership agreement and the originals or notarised copies of the signature circulars or signature declarations of the persons named in the agreement must be sent to the Agency via EBS with a standard petition.
A Roadmap from Scratch for a Newly Established Medical Company
In a company starting from scratch, the order goes as follows.
Sales centre authorisation certificate: Under Article 5 of the Medical Device Sales, Advertising and Promotion Regulation, a natural or legal person who wishes to be authorised as a sales centre applies to the directorate with a petition containing the address, title and ownership details of the sales centre; the documents listed in paragraph 2 of the same article are submitted with the petition.
ÇKYS number: Under paragraph 5 of Article 5 of the Guide, the ÇKYS number within the licence is added to the company registration in ÜTS.
ÜTS company registration: Under Article 5 of the Guide, it is made on the basis of MERSİS or VEDOP.
Document registration and document application: Carried out under Article 39 of the Guide.
Device registration and device application: Carried out under Article 40 of the Guide.
Paragraph 7 of Article 5 of the Guide also defines a convenience: when the company's responsible manager, title and address change, if the relevant information is updated in ÇKYS, these changes are updated automatically in ÜTS.
A Different Set-Up for Owners of Large Multi-Product Catalogues
For companies with hundreds of products, entering records one by one is not realistic. Articles 31, 32 and 33 of the Guide define the bulk addition and update route for devices under the former regulations, MDR and IVDR respectively.
The operation is the same in all three articles: from the "Bulk Transactions" area on the "List My Medical Devices" screen, the relevant bulk addition/update screen is opened, the template is downloaded from "Download Template Excel File", and the completed Excel file, together with the label information files and the packaging image files, is compressed in zip format to create the Notification Information File and uploaded to the "Zip File" field. The Guide requires these files to be directly inside the zip file, not in separate folders within it. Under paragraph 7 of Article 31, the Notification Information File may be at most 200 MB, and under paragraph 8, Turkish characters cannot be used in file names.
One point must not be overlooked: bulk upload does not complete the registration. Paragraph 10 of all three articles states that, for the suitability of the device registration or update notification made in this scope to be assessed, a device application must be made to the Agency under Article 40.
Taking Over a Rejected Process
When taking over a file that was started earlier and ended unfavourably, the first reflex is often to apply again. The Guide first shows another way. Paragraph 16 of Article 39 states that if a rejection or revision decision is thought to be contrary to the legislation and the Guide, a re-evaluation of the decision can be requested through the "Submit Request" screen before a new application is made. For device applications, the same route is defined in paragraph 9 of Article 40.
The same paragraphs also draw the limit of responsibility: the Agency is not held responsible for applications that are sent for review by applying again without being corrected through a request. In a file taken over, the right order is to first compare the rejection reasoning with the provisions of the Guide, to object if the reasoning is wrong, and to apply again after remedying the deficiency if the reasoning is correct.
Seven Questions to Ask Before Granting Authorisation
The questions below are not in the Guide; they are a checklist from practice. Having the answers in writing before opening the authorisation prevents most later disputes.
Which user type will be opened? The "Medical Device Registration Officer" or another type?
Which screens will be accessed? Which of the document, device, bulk transactions, free sale certificate and request screens are in scope?
Who keeps the e-signature? Who is the signatory authority, is there a deputy, and until when is the e-signature valid?
How will records be reported? How often, under which headings, and by which application numbers?
Who writes the requests and objections? Who carries the duty to cite the legislation?
Who follows the payment step? Who owns an application left in "Awaiting Payment" status?
When will the authorisation be closed? Who is responsible for updating the user list when the service ends?
Are "Getting ÜTS Registration Done" and "ÜTS Consultancy" the Same Thing?
In practice the two expressions are used in the same sense, but their scope differs.
Getting ÜTS registration done is transaction-oriented: you have documents and a product list, and you want them entered correctly into the system and the application created and approved. The result is the device reaching "Registered" status.
ÜTS consultancy is a broader frame. It covers determining which class the device is in, setting up which document combination that class requires, planning in which format missing documents will be requested from the manufacturer, deciding which route to follow in the MDR and IVDR transition, and building the objection strategy when a rejection or revision arises. Registration is the last step of this work.
Which one you need depends on the state of your file. For a catalogue with complete documents and a clear class, getting the registration done may be enough; for a file with unclear document set-up or with transition-period pressure, consultancy is needed first.
You can find how authorisation is opened and closed in ÜTS on our ÜTS Granting Authorisation to a Consultant page, the process specific to imported devices on our Imported Medical Device ÜTS Registration page, the document list on our Documents Required for ÜTS Registration page, and the bulk registration set-up on our ÜTS Bulk Product Registration page. For the service scope, see our ÜTS Registration Consultancy Service and ÜTS Registration Officer Authorisation pages.