ÜTS Registration During the MDR and IVDR Transition

The EC certificate or declaration of conformity of your device is under the old regulation and you need to benefit from the transition period. The real difficulty here

ÜTS Registration During the MDR and IVDR Transition: Dates and System Steps

The EC certificate or declaration of conformity of your device is under the old regulation and you need to benefit from the transition period. The real difficulty here is knowing until which date each device can be placed on the market, and making the application that makes this right visible in ÜTS in the correct order. This page gives all MDR and IVDR transition dates in four tables, and then describes the EBS and ÜTS steps in order.

All the dates below are taken from Articles 45 to 50 of the TİTCK Guide. First determine which group your device falls into; a date only has meaning together with the right group.

Basis of the Transition Provisions: (EU) 2023/607 and (EU) 2024/1860

The transition provisions rest on two EU Regulations and the parallel amendments to the national regulations. Paragraph 1 of Article 45 of the Guide states that Regulation (EU) 2023/607, prepared by the European Commission to reduce the risk of shortages of medical devices, entered into force on being published in the Official Journal of the EU on 20 March 2023. Paragraph 1 of Article 48 of the Guide states that Regulation (EU) 2024/1860 on the IVD side entered into force on being published on 09.07.2024.

The Turkish counterpart is written in the same two articles. Paragraph 2 of Article 45 and paragraph 2 of Article 48 of the Guide state that, in parallel, the “Regulation on Amendments to the Medical Device Regulation” and the “Regulation on Amendments to the In Vitro Diagnostic Medical Device Regulation” were published in Official Gazette No. 32151 of 2/4/2023, and that these amendments were reflected in the MDR and IVDR.

MDR Last Placing-on-the-Market Dates

Paragraphs 3 to 6 of Article 45 of the Guide determine, provided that the conditions in the Regulation are fulfilled, until which date four device groups can be placed on the market or put into service. The four rows below are the exact counterparts of these paragraphs.

  • Class III implantable custom-made medical devices under MDD: can be placed on the market or put into service until 26.05.2026. The basis is paragraph 3 of Article 45.

  • Class III devices and Class IIb implantable devices under MDD or AIMDD: until 31.12.2027. The basis is paragraph 4 of Article 45; some products listed in this paragraph are outside the scope.

  • Other Class IIb devices and Class IIa, Class Im and Class Is devices: until 31.12.2028. The basis is paragraph 5 of Article 45; this refers to devices under MDD that are not covered by paragraph 4.

  • Class I devices up-classified under MDR: until 31.12.2028. The basis is paragraph 6 of Article 45; these are devices whose conformity assessment under MDD did not require the involvement of a notified body, for which a declaration of conformity was drawn up before 26 May 2021, and which require a notified body under MDR.

Products Excluded from 31.12.2027

Paragraph 4 of Article 45 of the Guide explicitly excludes certain product groups from the 31.12.2027 date given for Class IIb implantable devices. The excluded ones are: sutures, staples, dental fillings, dental braces, dental crowns, screws, wedges, plates, wires, pins, clips and connectors.

Because these products are outside that scope, they fall within paragraph 5 among Class IIb devices under MDD and are subject to the 31.12.2028 date. If your product group is on this list, your calendar moves forward by a year, not back; missing this distinction leads to the extension application being made with the wrong date declaration.

MDR Extension Conditions and the Period Granted

The last placing-on-the-market dates do not operate by themselves; the conditions in Article 46 of the Guide must be met and the EBS application must be found suitable. The rows below show which condition brings which period.

  • EC certificate expiry date before 26.05.2021: Under subparagraph (a) of paragraph 3 of Article 46 of the Guide, no extension applies to devices covered by an EC certificate issued under MDD or AIMDD whose document expiry date is before 26.05.2021.

  • Class III implantable custom-made device, application before 26.05.2024: According to paragraph 2 of Article 46 of the Guide, provided that an application is made before 26.05.2024 to a notified body designated under MDR, if the application made with the Manufacturer’s Declaration and the Notified Body (NB) Acceptance Document is found suitable, the period for which the devices remain registered in ÜTS is extended until 26.09.2024.

  • Class III implantable custom-made device, contract before 26.09.2024: According to the same paragraph, provided that a contract is made before 26.09.2024 with a notified body designated under MDR, if the application made with the Manufacturer’s Declaration and the NB Confirmation Letter is found suitable, the period for remaining registered is extended until 26.05.2026.

  • Document expiry before 20.03.2023, contract before document expiry: According to subparagraph (b) of paragraph 3 of Article 46 of the Guide, for EC certificates valid on and after 26.05.2021 whose expiry date is before 20.03.2023, if the manufacturer applied to an MDR notified body and signed a contract before the document expiry date, the application is made with the Manufacturer’s Declaration, the NB Confirmation Letter and the document stating that surveillance responsibility has been assumed until 26.09.2024. According to subparagraph (e), the validity date of the certificate is extended until 31.12.2027 or 31.12.2028 according to the risk class of the device.

  • Document expiry before 20.03.2023, contract after document expiry: According to subparagraph (c) of the same paragraph, in this case the third document changes: instead of the surveillance document, an authorisation document obtained from the Agency under paragraph 1 of Article 59 of MDR, or a document issued by the Agency to the economic operator under paragraph 1 of Article 94 of MDR, is submitted. The result is again the 31.12.2027 or 31.12.2028 date in subparagraph (e).

  • Document expiry on or after 20.03.2023, application only: According to subparagraph (ç) of the same paragraph, for certificates whose expiry date falls on or after 20.03.2023, if the manufacturer applied to an MDR notified body before 26.05.2024, the application is made with the Manufacturer’s Declaration, the NB Acceptance Document and the surveillance document valid until 26.09.2024. According to subparagraph (f), the validity date of the certificate is extended until 26.09.2024.

  • Document expiry on or after 20.03.2023, application and contract in place: According to subparagraph (d) of the same paragraph, if an application was made before 26.05.2024 and a contract was made with this body before 26.09.2024, the Manufacturer’s Declaration, the NB Confirmation Letter and the surveillance document are submitted. According to subparagraph (g), the validity date of the certificate is extended until 31.12.2027 or 31.12.2028 according to the risk class.

  • Application for up-classified Class I devices: According to subparagraph (a) of paragraph 4 of Article 46 of the Guide, if an application was made to a notified body before 26.05.2024, then under subparagraph (c) the period for which the devices remain registered in ÜTS is extended until 26.09.2024.

  • Contract for up-classified Class I devices: According to subparagraph (b) of the same paragraph, if a contract was made with a notified body before 26.09.2024, then under subparagraph (ç) the period for remaining registered is extended until 31.12.2028.

  • Date commitments in the Manufacturer’s Declaration: Subparagraph (ç) of paragraph 5 of Article 46 of the Guide asks for statements that a quality management system under MDR Article 10(9) will be put in place no later than 26.05.2024; subparagraph (d) that a formal application has been made to a notified body under the first subparagraph of point 4.3 of MDR Annex VII no later than 26.05.2024; and subparagraph (e) that a written agreement has been signed under the second subparagraph of the same point no later than 26.09.2024.

IVDR Last Placing-on-the-Market Dates

The calendar on the IVD side is more graduated. Paragraphs 3 and 4 of Article 48 of the Guide define four groups, and each group has a different last date.

  • Annex-2 List-A, Annex-2 List-B and Self-Test Devices under IVDD: can be placed on the market or put into service until 31.12.2027. The basis is paragraph 3 of Article 48.

  • Class D group under IVDR: until 31.12.2027. The basis is subparagraph (a) of paragraph 4 of Article 48, and it covers devices to be classified as Class D, Self-Test Device (Class D), Near-Patient Test Device (Class D) and Companion Diagnostic Device (Class D).

  • Class C group under IVDR: until 31.12.2028. The basis is subparagraph (b), and it covers Class C, Self-Test Device (Class C), Near-Patient Test Device (Class C) and Companion Diagnostic Device (Class C) devices.

  • Class B, Near-Patient Test Device (Class B) and Class A Sterile under IVDR: until 31.12.2029. The basis is subparagraph (c).

The opening sentence of paragraph 4 sets one more condition: these three subparagraphs apply to devices whose conformity assessment procedure under IVDD did not require the involvement of a notified body, for which a declaration of conformity was drawn up before 26 May 2022, and which require a notified body under IVDR.

IVDR Extension Conditions and the Period Granted

The extension conditions on the IVDR side are regulated in Article 49 of the Guide, and they operate separately for certified devices and for up-classified devices.

  • EC certificate expiry before 26.05.2022: Under subparagraph (a) of paragraph 2 of Article 49 of the Guide, no extension applies to devices covered by an EC certificate issued under IVDD whose document expiry date is before 26.05.2022.

  • Document expiry before 09.07.2024, contract before document expiry: According to subparagraph (b) of the same paragraph, for certificates valid on and after 26.05.2022 whose expiry date is before 09.07.2024, if the manufacturer applied to an IVDR notified body and signed a contract before the document expiry, the Manufacturer’s Declaration, the NB Confirmation Letter and the surveillance responsibility document valid until 26.09.2025 are submitted. According to subparagraph (f), the validity date of the certificate is extended until 31.12.2027.

  • Document expiry before 09.07.2024, contract after document expiry: According to subparagraph (c) of the same paragraph, the third document changes: an authorisation document obtained from the Agency under paragraph 1 of Article 56 of IVDR, or a document issued by the Agency to the economic operator under paragraph 1 of Article 91 of IVDR, is submitted. The result is again the 31.12.2027 date in subparagraph (f).

  • Document expiry on or after 09.07.2024, no application made: According to subparagraph (ç) of the same paragraph, if the manufacturer has not applied to an IVDR notified body, the Manufacturer’s Declaration and the surveillance responsibility document valid until 26.05.2025 are submitted. According to subparagraph (g), the validity date of the certificate is extended until 26.05.2025.

  • Document expiry on or after 09.07.2024, application before 26.05.2025: According to subparagraph (d) of the same paragraph, the Manufacturer’s Declaration, the NB Acceptance Document and the surveillance document valid until 26.09.2025 are submitted. According to subparagraph (ğ), the validity date is extended until 26.09.2025.

  • Document expiry on or after 09.07.2024, application and contract in place: According to subparagraph (e) of the same paragraph, if an application was made before 26.05.2025 and a contract before 26.09.2025, the Manufacturer’s Declaration, the NB Confirmation Letter and the surveillance document are submitted. According to subparagraph (h), the validity date is extended until 31.12.2027.

  • Application dates for up-classified devices: According to subparagraph (a) of paragraph 3 of Article 49 of the Guide, the application to a notified body must be made before 26.05.2025 for the Class D group, before 26.05.2026 for the Class C group, and before 26.05.2027 for the Class B, Near-Patient Test Device (Class B) and Class A Sterile group. If the application is found suitable under subparagraph (c), the period for which the devices remain registered in ÜTS and the validity period of the declaration of conformity are extended until 26.09.2025, 26.09.2026 and 26.09.2027 respectively.

  • Contract dates for up-classified devices: According to subparagraph (b) of the same paragraph, the contract with the notified body must be made before 26.09.2025 for the Class D group, before 26.09.2026 for the Class C group and before 26.09.2027 for the Class B group. If the application is found suitable under subparagraph (ç), the period for remaining registered and the validity period of the declaration of conformity are extended until 31.12.2027, 31.12.2028 or 31.12.2029, according to the risk class of the device.

Chronological Calendar: All Dates from 2023 to 2029

The four tables above are read by device group. Seeing the same dates in chronological order makes planning your own calendar easier.

  • 20.03.2023: Regulation (EU) 2023/607 entered into force on being published in the Official Journal of the EU. The same date is also used as the EC certificate expiry date threshold in paragraph 3 of Article 46 of the Guide.

  • 02.04.2023: The amendments to the Medical Device and In Vitro Diagnostic Medical Device regulations were published in Official Gazette No. 32151.

  • 26.05.2024: Deadline on the MDR side for the quality management system and the formal application to a notified body.

  • 09.07.2024: Regulation (EU) 2024/1860 entered into force. The same date is the IVDD EC certificate expiry date threshold in paragraph 2 of Article 49 of the Guide.

  • 26.09.2024: Deadline on the MDR side for the written agreement with the notified body and surveillance responsibility.

  • 26.05.2025 and 26.09.2025: Application and contract thresholds for the IVDR Class D group; also the surveillance responsibility dates for IVDD certificates.

  • 26.05.2026 and 26.09.2026: Application and contract thresholds for the IVDR Class C group.

  • 26.05.2026: Last placing-on-the-market date for Class III implantable custom-made devices under MDD.

  • 26.05.2027 and 26.09.2027: Application and contract thresholds for the IVDR Class B, Near-Patient Test (Class B) and Class A Sterile group.

  • 31.12.2027: On the MDR side, Class III and Class IIb implantable devices other than the excluded ones; on the IVDR side, the last date for Annex-2 List-A, List-B, Self-Test Devices and the Class D group.

  • 31.12.2028: On the MDR side, other Class IIb, Class IIa, Class Im, Class Is and up-classified Class I devices; on the IVDR side, the last date for the Class C group.

  • 31.12.2029: On the IVDR side, the last date for Class B, Near-Patient Test Device (Class B) and Class A Sterile devices.

A Two-Stage Structure: First EBS, Then ÜTS

Benefiting from the transition provisions does not happen with a single application. Paragraph 7 of Article 45 of the Guide states that, for companies to benefit from the MDR transition provisions for their devices within paragraphs 3 to 6, they must first apply through EBS under Article 46, and if the application is found suitable, make a registration/update application in ÜTS under Article 47 for the relevant devices and linked documents. Paragraph 5 of Article 48 of the Guide sets up the same structure on the IVDR side through Articles 49 and 50.

The EBS application is made through the Agency’s Electronic Application System, selecting “2023/KK-1 Numbered Period Extension Application” as the application document type, without physical papers. Paragraph 8 of Article 46 and paragraph 7 of Article 49 of the Guide add that applications without a petition are not accepted and that the petition must state the document for which the transition period is requested.

The “Document Application under Announcement No. 2023/KK-1” in ÜTS

After the EBS stage ends positively, a separate application type is used in ÜTS. Subparagraph (ç) of paragraph 4 of Article 39 of the Guide defines this type as “Document Application under Announcement No. 2023/KK-1”; paragraph 8 of the same article states that this type is selected for the document applications mentioned in Articles 47 and 50 of the Guide. Subparagraph (g) of paragraph 3 of Article 47 of the Guide also says that after the document registration/update notification is created, the document application is created by selecting this type at the application stage.

This field appearing on the screen depends on another selection. According to subparagraph (b) of paragraph 3 of Article 47 of the Guide, if “90/385/EEC” or “93/42/EEC” is selected in the “Regulation It Belongs To” field on the “Update Document” screen, the field “Is this a Document Registration/Update Notification Application under Announcement No. 2023/KK-1?” appears. Subparagraph (b) of paragraph 2 of Article 50 of the Guide states that on the IVDR side the same field opens when “98/79/EC” is selected. If the regulation field is not selected correctly, the 2023/KK-1 field does not appear at all.

The “Evidence Documents for MDR Transition Period Extension” Field

When the 2023/KK-1 field is set to “Yes”, a mandatory document field opens on the screen. Subparagraph (c) of paragraph 3 of Article 47 of the Guide names this field “Evidence Documents for MDR Transition Period Extension”; its counterpart on the IVDR side is the “Evidence Documents for IVDR Transition Period Extension” field in subparagraph (c) of paragraph 2 of Article 50.

What is uploaded to the field is listed in subparagraphs (ç) of paragraphs 2 and 3 of Article 47 of the Guide: the Confirmation Letter sent to the company by the Agency after the EBS application, containing statements that the period extension has been permitted, together with all the statements and documents in the application made under Article 46, are uploaded complete with all their pages, in a single file.

The approval format differs in this field. Subparagraphs (d) of paragraphs 2 and 3 of Article 47 and subparagraph (d) of paragraph 2 of Article 50 of the Guide state that no apostille or notarial approval is required for these documents; on the other hand, the Turkish translations of documents whose original is in a foreign language must be certified by a sworn translator.

Which Date Is Entered in the Document Expiry Date Field?

This is the question asked most often in extension applications, and its answer is counter-intuitive. Subparagraph (e) of paragraph 3 of Article 47 of the Guide states that the original expiry date of the relevant EC certificate is entered in the “Document Expiry Date” field on the document registration/update screen; if the application is found suitable, this date is updated by the Agency as stated in subparagraph (ğ) of the same paragraph. Subparagraph (e) of paragraph 2 of Article 50 of the Guide repeats the same rule on the IVDR side.

That is, you do not write the extended date yourself. When the application is found suitable under subparagraph (ğ), the certificate is brought to “Registered” status in ÜTS and the “Document Expiry Date” is updated by the Agency to the date stated in the Confirmation Letter. Subparagraph (e) of paragraph 4 of Article 47 of the Guide adds that for declarations of conformity of unlimited duration, no date is entered in this field at all.

Two Different Flows for Limited-Duration and Unlimited-Duration Declarations of Conformity

After the period extension has been granted to the certificate, the declaration of conformity linked to it must also remain in “Registered” status. Subparagraph (h) of paragraph 3 of Article 47 and subparagraph (h) of paragraph 2 of Article 50 of the Guide divide this flow in two according to the duration status of the declaration.

  • Limited-duration declaration that is registered in ÜTS: Without creating a new document registration/update application, a request is created using the “Report Request” screen and selecting “MDR/IVDR Period Extension” as the “Request Area”. Entering the declaration’s Document Number in ÜTS in the request is mandatory.

  • Limited-duration declaration that is not registered in ÜTS: According to subparagraph (ı), the application is first made on the “Document Registration/Update” screen by selecting “Yes” for “Is it of unlimited duration?” and without entering a document expiry date; then a request is created from the “MDR/IVDR Period Extension” request area.

  • Unlimited-duration declaration: According to the fourth sub-subparagraphs of the same subparagraphs, these transactions are not made. If the declaration is not in “Registered” status in ÜTS, a normal document registration/update application is made under Articles 12 or 13 and Article 39 of the Guide.

The name of the request area also appears in paragraph 19 of Article 46 and paragraph 18 of Article 49 of the Guide: ÜTS requests relating to these processes are created by selecting the “MDR/IVDR Period Extension” request area, and the transaction tracking number of the relevant EBS application is added to the request.

Evaluation Request under Announcement No. 2024/KK-3

A separate request flow is defined for limited-duration declarations of conformity that are not registered in ÜTS. The second sub-subparagraph of subparagraph (ı) of paragraph 3 of Article 47 and the second sub-subparagraph of subparagraph (ı) of paragraph 2 of Article 50 of the Guide state that after the document registration/update application is created for the declaration, a request is created from the “Report Request” screen by selecting “MDR/IVDR Period Extension”, so that the application is evaluated under “Announcement No. 2024/KK-3”. In this request, entering the relevant Document Application Number in the “Medical Device/Document Application Number” field is mandatory.

If a ÜTS Application Is Made Without EBS Approval

Skipping the order is a direct ground for rejection. Subparagraph (a) of paragraph 3 of Article 47 of the Guide states that, in order for an MDR transition period to be defined for an EC certificate, an application must be made in EBS under Article 46 and the Agency must permit the period extension before the document registration/update application is made in ÜTS; if no application is made in EBS and no permission is given, the ÜTS application will be rejected. Subparagraph (a) of paragraph 2 of Article 50 of the Guide repeats the same result on the IVDR side. Subparagraph (a) of paragraph 2 of Article 47 of the Guide sets the same rule for the ITC application in custom-made device applications.

Linking a Device That Moved to MDR with a Different Barcode to Its Old Record

If the device is placed on the market with a new barcode during the transition, the new record must be associated with the old record. Subparagraph (c) of paragraph 2 of Article 27 of the Guide states that the field “Did it transition to MDR with a different product number?” is mandatory and that “Yes” is selected if the device was previously registered in ÜTS under MDD or AIMDD with a different barcode. Subparagraph (ç) states that when “Yes” is selected, the primary product number of the old record is selected from the “Product Number in 93/42/EEC or 90/385/EEC” field that opens, and that only a single barcode can be selected in this field.

Its counterpart on the IVDR side is subparagraphs (c) and (ç) of paragraph 2 of Article 30 of the Guide: the field “Did it transition to IVDR with a different product number?” and the field “Product Number in 98/79/EC” that opens when “Yes” is selected. On both sides the old record is found by querying with the “Primary Product Number”, “Brand Name”, “Product Name” and “Version/Model” fields.

Up-Classified Class I Devices

This group is often overlooked because it has no certificate. Paragraph 6 of Article 45 of the Guide defines the group: devices whose conformity assessment procedure under MDD did not require the involvement of a notified body, for which a declaration of conformity was drawn up before 26 May 2021, and which require notified body involvement under MDR. The paragraph describes them as “devices that were Class I Other devices under MDD but whose class is raised under MDR” and gives the last date as 31.12.2028.

In this group the extension is defined not on a certificate but on the declaration of conformity. Paragraph 4 of Article 46 of the Guide states that if an application is made to a notified body before 26.05.2024, the registered period is extended until 26.09.2024, and if a contract is made before 26.09.2024, until 31.12.2028. Paragraph 4 of Article 47 of the Guide also defines the ÜTS steps through the declaration of conformity and states in subparagraph (b) that if “93/42/EEC” is selected in the “Regulation It Belongs To” field, the 2023/KK-1 field opens.

26.05.2026 for Custom-Made Class III Implants

For custom-made devices the process runs through the ITC screen. Subparagraph (ç) of paragraph 12 of Article 29 of the Guide states that “Yes” is selected in the “Is it a Class III implantable custom-made medical device?” field for the relevant device; subparagraph (d) states that if “Yes” is selected, filling in the field “Was an application made under Announcement No. 2023/KK-1?” that appears is mandatory. If this field is “Yes”, the “Evidence Documents for MDR Transition Period Extension” field in subparagraph (e) opens; if “No”, the “EU Certificate” field in subparagraph (f) opens. Subparagraph (b) of paragraph 2 of Article 47 of the Guide repeats the same screen flow.

The period comes from paragraph 2 of Article 46 of the Guide: if an application is made to a notified body before 26.05.2024, the registered period is extended until 26.09.2024, and if a contract is made before 26.09.2024, until 26.05.2026. According to subparagraph (g) of paragraph 2 of Article 47 of the Guide, if the application is found suitable, the ITC is brought to “Registered” status and the period for which the device remains in ÜTS is extended until the date stated in the Confirmation Letter.

The Transition Period Does Not Postpone Registration and Vigilance Obligations

The transition period allows the device to remain on the market; it does not suspend obligations. Subparagraph (d) of paragraph 5 of provisional Article 1 of the Medical Device Regulation states that, for the devices referred to in subparagraphs (b) and (c) of the same paragraph, the requirements of the Regulation on post-market surveillance, market surveillance and inspection, vigilance, and the registration of economic operators and devices apply instead of the corresponding requirements in the repealed regulations.

In practice this means the following: even if your device can remain on the market until 31.12.2028, the ÜTS registration, economic operator registration, post-market surveillance and vigilance obligations already operate under the provisions of the new regulation.

What Happens to the ÜTS Record of a Device Whose Certificate Has Expired?

If the extension conditions are not met, the period for which the device remains registered in ÜTS ends. Paragraphs 2 and 3 of Article 46 and paragraphs 2 and 3 of Article 49 of the Guide provide that the periods of remaining registered and the certificate validity dates will be extended only if the listed conditions are met and the application is found suitable. If one of the conditions is missing, for example if the EC certificate’s expiry date is before 26.05.2021 on the MDR side or before 26.05.2022 on the IVDR side, no extension applies at all.

The period extension application itself is a separate piece of work: the EBS file must be prepared, the Manufacturer’s Declaration and the NB Confirmation Letter or NB Acceptance Document must be checked for compliance with the minimum content requirements, the sworn translations must be completed, and then the document registration must be made in ÜTS with the correct application type. Companies can also carry out this work by granting user authority to a consultant from their own ÜTS company pages; the consultant creates and approves the records with the “Medical Device Registration Officer” authority, while the person who signs the application electronically remains the company’s signatory under paragraph 13 of Article 39 of the Guide.

For the counterpart on the EU side, our MDR/IVDR transition deadline checker page (in English) is a guide.

ÜTS Registration

Medical Device ÜTS Registration Consultancy

Request an ÜTS registration consultancy quote

Ehlibeyt Mahallesi, Tekstilciler Caddesi No: 35/7 06520 Çankaya / Ankara - TÜRKİYE

Cevizli Mahallesi, Zuhal Caddesi Ritim İstanbul B Blok, No:44 Maltepe / İstanbul - TÜRKİYE

info@medexmedikal.com
+90 505 580 4622
+90 312 389 1354

ÜTS Guides · Legislation Calendar · Glossary · ÜTS Guide Index · Frequently Asked Questions

Services: ÜTS Consultancy · Who Carries Out the ÜTS Registration? · ÜTS Document Registration Consultancy · ÜTS Product Registration Consultancy · Importer ÜTS Registration Consultancy · Sales Centre Authorisation Certificate · EUDAMED Registration Consultancy · MDR/IVDR Declaration of Conformity · Technical File Preliminary Review · Label and Instructions for Use Check · PRRC Service · PMS and PSUR · Clinical Evaluation · EMDN and GMDN Code Determination · Certificate of Free Sale · EUDAMED XML Generator · ÜTS Registration Training · Correction of a Rejected ÜTS Application

KVKK and Privacy Policy | Cookie Policy | Accessibility Statement

© 2026 Medex Kurumsal Danışmanlık Ltd. Şti.

bottom of page
WhatsApp Hemen Ara